31 July 2012
3G Pitch Latest News
Despite some rumours to the contrary, our 3G pitch project is still ploughing ahead, with the committee working overtime at the moment to get the project over the line. Tests were carried out on the site back in May, with the company employed producing a report that detailed the level of drainage required on the project to allow companies to tender as acurately as possible. The tenders were then sent out at the end of June with a 3 week turnaround asked for. The committee last week reviewed all the tenders received for the project along with our project manager and have notified the preferred contractor, however, there are still some negotiations to go through to get the pitch that we want for the money available. The old metaphor of the duck has never been so apt as on this project, with the site at Seven Acres appearing calm with nothing happening, whilst the committee are paddling furiously underneath to push it forward. Keep an eye on the website for any further developments.