03 July 2014
3G Pitch Update
Progress against the construction programme is going to plan. The main fence is being erected and is due to be completed by 08 Jul Once done the playing surface will start to arrive; this is due 12 Jul, this will then take about four weeks to lay. Further work is still being carried out on the new car park with tarring due to start on or about 22 Jul. As of today the flood light are starting to be erected. We are very much on course for the pitch to be ready for 01 September.
There is an Open Evening on 16 July where the Construction Director is inviting residents to visit the pitch where he will walk you over it and explain what is going on.