30 May 2014
3G Pitch Update
The end of week 6 and all the earthworks, drainage have been completed, with kerbing 40% done. Currently the construction is 1 week ahead of schedule mainly due to the good weather we've been having. The main fence is to start being erected on 16 June and by then all kerbing, carpark surface will be completed. The next on the agenda will be the construction of the floodlight bases, carpark kerbing, retaining wall and the forming of the hardstanding. It is now starting to come together and with a bit of imagination you can see what it will look like.